Project: MattJ   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Matt Jakus   -  
Project:   The Airplane Factory - Sling TSi   -   VIEW REPORTS
Total Hours:1190.7
Start/Last Date:Dec 01, 2019 - Jan 29, 2023
Engine:Rotax 915is
Panel:Garmin 3X
 
Friendly URL: https://eaabuilderslog.org?s=MattJ

Home or Last Project Picture

Mar 25, 2020     Horizontal Stabilzer - (36.5 hours)       Category: Empennage
Empennage is divided into 3 build sections per the kit. First is the stabilizer, next elevator, finally the rudder. I'm am missing a central part on the elevator section so I can do the stabilizer then the rudder.

Stabilizer:

Pull plastic off parts. counter-sink drill certain holes that will line up with the dimpled skin. De-burr edges and rivet holes. Cleco and test fit parts.

Parts fit pretty well. The nose ribs required delicate work to get the rivets set without inadvertently bending the part. Camera probe was used to check all the setting of the rivets. Electric Trim motor wiring was positioned.

Skins lined up and square was checked.


 